What does approved AS NOTED mean?

What does approved AS NOTED mean?

APPROVED AS NOTED Indicates that work may proceed provided that it complies with the notations or corrections on the submittal and contract documents. Some organizations might want to rename this ‘APPROVED AS CORRECTED’ or ‘FURNISH AS NOTED’ or ‘REVIEWED CORRECTIONS NOTED. ‘

What is reviewed as noted?

REVIEWED AS NOTED means that the Contractor may proceed with manufacture, fabrication or construction providing the Designer’s notations are incorporated into the work. Re-submittal is not required unless the Contractor is unable to comply with the notations.

Does reviewed mean approved?

Apparently, the word “approved” implies an absolute confirmation that the word “reviewed” does not. Remember, though, that the design professional is supposed to be judged by whether that professional performed services, including submittal review, in accordance with the standard of care.

What is the difference between noted and approved?

As adjectives the difference between approved and noted is that approved is having received approval while noted is famous; well known because of one’s reputation; celebrated.

What does make corrections noted mean?

Related Definitions Make Corrections Noted means that fabrication, manufacture, or construction may proceed providing submittal complies with Engineer’s notation and Contract Documents. If, for any reason, notations cannot be complied with, resubmit as described for submittals stamped “Reject”.

What does no exception taken mean?

The term “no exceptions taken” means that we have in fact looked at/reviewed the shop drawings and we don’t see anything particular that is wrong with them. The reason that “approved” and “accepted” are wrong is because they imply that we swear by these drawings and that our approval will make us responsible.

What does stamping drawings mean?

The Board issues stamps to license holders as a means to signify to Permitting Authorities and the General Public that the architectural document has been prepared under the direct supervision of an Architect. Architectural drawings, including design and construction drawings.

Does no exceptions taken mean approved?

No Exceptions Taken means that fabrication, manufacture, or construction may proceed providing submittal complies with contract documents. But it does not constitute approval or deletion of specified or required items not shown in the partial submittal.

What is higher noted or approved?

Where do you put noted in a letter?

Enclosures are noted at the bottom left of the letter, a couple of spaces below your signature, followed by a list of the documents included.

What does no exception mean in submittals?

No Exception Taken, means that fabrication, manufacture, or construction may proceed providing submittal complies with Contract Documents.

How many approved images of stamps are there?

130,042 approved stamp stock photos, vectors, and illustrations are available royalty-free.

Where can I get drawing and review stamps?

While finding the right choice for your professional stamp needs can seem like a hassle, our inventory of engineering and architect shop drawing review stamps makes it easy and affordable to get the tool you need for the job. We offer engineering and architect submission stamps in a variety of options to fit your needs.

How does an architect approve a contractor stamp?

Contractor stamps submittal approved. When the marked-up submittal is found to be acceptable, the contractor affixes a review stamp with a signature and date. Contractor submits to architect. Only after the contractor’s approval is the submittal sent to the architect with an attached transmittal.

Which is engineering and engineering shop drawing review stamps?

From reviewing plans to approval notices, our selection of architect and engineering shop drawing review stamps are the perfect solution.